76 lines
2.1 KiB
Markdown
76 lines
2.1 KiB
Markdown
---
|
|
gsd_state_version: 1.0
|
|
milestone: v1.0
|
|
milestone_name: milestone
|
|
current_plan: 0
|
|
status: planned
|
|
last_updated: "2026-04-28T08:30:48.000Z"
|
|
progress:
|
|
total_phases: 11
|
|
completed_phases: 1
|
|
total_plans: 14
|
|
completed_plans: 7
|
|
percent: 50
|
|
---
|
|
|
|
# Project State: Recipe
|
|
|
|
**Project reference:** `.planning/PROJECT.md`
|
|
**Roadmap:** `.planning/ROADMAP.md`
|
|
**Requirements:** `.planning/REQUIREMENTS.md`
|
|
|
|
## Core Value
|
|
|
|
"My week is planned." I pick recipes, the calendar fills up, and I know what we're eating. Everything else — pantry tracking, shopping list, nutrition numbers — exists to reinforce that one moment.
|
|
|
|
## Current Position
|
|
|
|
Phase: 02 — Authentication Foundation — PLANNED
|
|
Plan: 0 of 7
|
|
**Current focus:** Phase 2 ready for execution
|
|
**Current plan:** 0
|
|
**Status:** Phase 2 planning complete; ready to execute Phase 2
|
|
**Phase progress:** 1 / 11 phases complete
|
|
**Progress bar:** `██░░░░░░░░░░░░░░░░░░` 9%
|
|
|
|
## Performance Metrics
|
|
|
|
| Metric | Value |
|
|
|--------|-------|
|
|
| Phases planned | 11 |
|
|
| v1 requirements | 72 |
|
|
| Coverage | 100% |
|
|
| Phases complete | 1 |
|
|
| Plans complete | 7 |
|
|
|
|
## Accumulated Context
|
|
|
|
### Decisions carried in
|
|
|
|
All locked tech-stack decisions are captured in `.planning/PROJECT.md § Key Decisions`. Architectural patterns are in `.planning/research/ARCHITECTURE.md`. High-risk pitfalls by phase are in `.planning/research/PITFALLS.md`. Do not re-relitigate locked decisions during phase planning.
|
|
|
|
### Open todos
|
|
|
|
- None.
|
|
|
|
### Blockers
|
|
|
|
- None.
|
|
|
|
## Session Continuity
|
|
|
|
**Last session:** --stopped-at
|
|
|
|
**Next action:** `/gsd-execute-phase 2` — Authentication Foundation.
|
|
|
|
**Research flags to revisit during future phase planning:**
|
|
|
|
- Phase 4 (SyncEngine): concrete cursor format, outbox schema ordering guarantees, retry/backoff policy.
|
|
- Phase 10 (UI chrome): current Haze CMP-iOS perf on iPhone 11/12-era hardware; liquid-glass approximation patterns.
|
|
|
|
---
|
|
*Last updated: 2026-04-28*
|
|
|
|
**Planned Phase:** 1 (Project Infrastructure & Module Wiring) — 7 plans — 2026-04-24T16:07:36.289Z
|
|
**Planned Phase:** 2 (Authentication Foundation) — 7 plans — 2026-04-28T08:30:48.000Z
|