gsd_state_version: 1.0
milestone: v1.0
milestone_name: milestone
current_plan: 7
status: phase-complete
last_updated: "2026-04-24T18:56:34.969Z"
progress:
total_phases: 11
completed_phases: 1
total_plans: 7
completed_plans: 7
percent: 100
---
# Project State: Recipe
**Project reference:** `.planning/PROJECT.md`
@@ -10,11 +25,13 @@
## Current Position
**Current focus:** Phase 1: Project Infrastructure & Module Wiring
**Current plan:**
**Status:** Roadmap created; no plan started yet
**Phase progress:** 0 / 11 phases complete
**Progress bar:** `░░░░░░░░░░░░░░░░░░░░` 0%
Phase: 01 — Project Infrastructure & Module Wiring — COMPLETE
Plan: 7 of 7
**Current focus:** Phase 1 automated gate complete
**Current plan:** 7
**Status:** Phase 1 complete; ready to plan Phase 2
**Phase progress:** 1 / 11 phases complete
**Progress bar:** `██░░░░░░░░░░░░░░░░░░` 9%
## Performance Metrics
@@ -23,8 +40,8 @@
| Phases planned | 11 |
| v1 requirements | 72 |
| Coverage | 100% |
| Phases complete | 0 |
| Plans complete | 0 |
| Phases complete | 1 |
| Plans complete | 7 |
## Accumulated Context
@@ -34,7 +51,7 @@ All locked tech-stack decisions are captured in `.planning/PROJECT.md § Key Dec
### Open todos
- None yet — first action is `/gsd-plan-phase 1`.
- None.
### Blockers
@@ -42,14 +59,17 @@ All locked tech-stack decisions are captured in `.planning/PROJECT.md § Key Dec
## Session Continuity
**Last session:** Roadmapping session, 2026-04-23. Produced `ROADMAP.md` with 11 phases and `STATE.md`; updated `REQUIREMENTS.md` traceability table.
**Last session:** Completed 01-07-PLAN.md
**Next action:** `/gsd-plan-phase 1` — decompose Phase 1 (Project Infrastructure & Module Wiring) into plans.
**Next action:** `/gsd-discuss-phase 2` or `/gsd-plan-phase 2` — Authentication Foundation.
**Research flags to revisit during phase planning:**
- Phase 2 (Auth): Authentik-specific OIDC setup; iOS OIDC wrapper library choice; token refresh behavior.
- Phase 4 (SyncEngine): concrete cursor format, outbox schema ordering guarantees, retry/backoff policy.
- Phase 10 (UI chrome): current Haze CMP-iOS perf on iPhone 11/12-era hardware; liquid-glass approximation patterns.
---
*Last updated: 2026-04-23*
*Last updated: 2026-04-24*
**Planned Phase:** 1 (Project Infrastructure & Module Wiring) — 7 plans — 2026-04-24T16:07:36.289Z