docs(01-07): complete phase gate plan

This commit is contained in:
2026-04-24 20:59:21 +02:00
parent 68655eae1a
commit 42d134a997
10 changed files with 193 additions and 31 deletions

View File

@@ -2,15 +2,15 @@
gsd_state_version: 1.0
milestone: v1.0
milestone_name: milestone
current_plan: 1
status: executing
last_updated: "2026-04-24T17:39:22.205Z"
current_plan: 7
status: phase-complete
last_updated: "2026-04-24T18:56:34.969Z"
progress:
total_phases: 11
completed_phases: 0
completed_phases: 1
total_plans: 7
completed_plans: 4
percent: 57
completed_plans: 7
percent: 100
---
# Project State: Recipe
@@ -25,13 +25,13 @@ progress:
## Current Position
Phase: --phase (01) — EXECUTING
Plan: 1 of --name
**Current focus:** Phase --phase — 01
**Current plan:** 1
**Status:** Executing Phase --phase
**Phase progress:** 0 / 11 phases complete
**Progress bar:** `░░░░░░░░░░░░░░░░░░░░` 0%
Phase: 01 — Project Infrastructure & Module Wiring — COMPLETE
Plan: 7 of 7
**Current focus:** Phase 1 automated gate complete
**Current plan:** 7
**Status:** Phase 1 complete; ready to plan Phase 2
**Phase progress:** 1 / 11 phases complete
**Progress bar:** `██░░░░░░░░░░░░░░░░░░` 9%
## Performance Metrics
@@ -40,8 +40,8 @@ Plan: 1 of --name
| Phases planned | 11 |
| v1 requirements | 72 |
| Coverage | 100% |
| Phases complete | 0 |
| Plans complete | 0 |
| Phases complete | 1 |
| Plans complete | 7 |
## Accumulated Context
@@ -51,7 +51,7 @@ All locked tech-stack decisions are captured in `.planning/PROJECT.md § Key Dec
### Open todos
- None yet — first action is `/gsd-plan-phase 1`.
- None.
### Blockers
@@ -59,9 +59,9 @@ All locked tech-stack decisions are captured in `.planning/PROJECT.md § Key Dec
## Session Continuity
**Last session:** --stopped-at
**Last session:** Completed 01-07-PLAN.md
**Next action:** `/gsd-plan-phase 1` — decompose Phase 1 (Project Infrastructure & Module Wiring) into plans.
**Next action:** `/gsd-discuss-phase 2` or `/gsd-plan-phase 2` — Authentication Foundation.
**Research flags to revisit during phase planning:**
@@ -70,6 +70,6 @@ All locked tech-stack decisions are captured in `.planning/PROJECT.md § Key Dec
- Phase 10 (UI chrome): current Haze CMP-iOS perf on iPhone 11/12-era hardware; liquid-glass approximation patterns.
---
*Last updated: 2026-04-23*
*Last updated: 2026-04-24*
**Planned Phase:** 1 (Project Infrastructure & Module Wiring) — 7 plans — 2026-04-24T16:07:36.289Z